Proctor & Gamble Plant Expansion

Project Details

Inception Date: October 2016 (concrete)
                          January 2017 (steel)
Completion Date: July 2017 (concrete)
                             May 2017 (steel)
Contract Amount: $3.6 milllion (concrete)
                             $1.4 million (steel)
Construction Type: Subcontractor - Hard Bid

Project Contacts

Owner:

Proctor & Gamble Co.
Lima, OH


General Contractor:

Fluor Corp.
Irving, TX
Contact: Glenn Horstman

Subcontractor:

Tuttle Construction, Inc.
Lima, OH
Project Manager: Tom Thomas

Sprint Cup Project

Project Scope

Proctor & Gamble Co. in Lima, OH and general contractor, Fluor Corp based in Irving, TX subcontracted with Lima-based Tuttle Construction for the concrete and steel components of the massive $65 million plant expansion of the laundry detergent manufacturing facility. 

Tuttle Construction erected the steel for the new three-story 80,000 square-foot manufacturing plant addition and installed all concrete building foundations, eleveated slabs and slab-on-grade of the facility. Tuttle was also responsible for underground plumbing, building grounding and miscellaneous concrete structures within the building footprint.

Contract amounts:

  • $3.6 million (concrete)
  • $1.4 million (steel)

 