Inception Date: January 2001
Completion Date: August 2001
Contract Amount: $3,269,895
Construction Type:
Design / Build

Project Contacts

Owner:

Columbus Health Department
Columbus, OH

Construction Manager:

Elford, Inc.
Columbus, OH
Contact: Sami Ayyash, 614-488-4000

Architect:

The Design Group, Inc.
Columbus, OH

General Contractor:

Tuttle Construction, Inc.
Project Manager: Rob Brown
Site Superintendents: Jeff Easton & Rick Stuber

Downtown Columbus Parking Garage

Project Scope

The 210,062 square foot open parking structure was designed and constructed by Tuttle Construction. The entire structure was constructed with pre-cast concrete. The garage houses 2 levels and occupies 700 parking spaces.

Project Accomplishments

There were zero lost time accidents on this project. The biggest challenge faced on this project was the high level of coordination required to keep the job running smoothly. The project is located downtown Columbus, Ohio, making it very difficult to get materials in and out due to the volume of traffic. The project was completed within the owner's budget and on schedule. Major earthwork was done at night so dirt could be hauled out without interrupting neighborhood traffic. Pre cast planks were 60' long which required special coordination to get them through the city and on to the site.